Modular Cath Labs During Hospital Renovations: How to Maintain Cardiac Program Continuity

A cath lab renovation creates an unusual planning challenge for hospitals: the project is designed to improve cardiac services, but completing it may temporarily take critical procedural space out of operation.

The construction schedule is only part of the problem.



Hospital leaders also have to decide what happens to procedures, physicians, staff, patients, and workflows while the permanent lab is unavailable.


A modular cath lab for hospital renovation can provide temporary procedural capacity on-site while work progresses inside the permanent facility. Atlas Medical specifically positions its modular cath lab rentals for renovations, temporary capacity, and projects where hospitals need to keep cases running.


The key is to treat the modular lab as part of the renovation strategy—not as equipment that gets added after the construction plan is already finished.

The Renovation Plan Needs

a Clinical Continuity Plan

When a permanent cath lab goes offline, the impact extends beyond the room itself.


Hospital teams need to determine how procedural capacity will be maintained during the construction period.


That can involve questions such as:

  • Which procedures need to continue?
  • How much capacity will be unavailable?
  • How long will the permanent lab be offline?
  • Where will scheduled cases be performed?
  • How will urgent cases be handled?
  • Will patients need to be transferred?
  • How will staff workflows change?
  • What happens if construction takes longer than planned?


Atlas's existing temporary cath lab guidance identifies reduced procedural capacity as one of the primary challenges hospitals face during cath lab replacement and upgrades.


Instead of addressing these questions after construction begins, hospitals can make continuity planning part of the renovation schedule from the start.



Think in Terms of Two Projects, Not One

A useful way to approach a cath lab renovation is to recognize that the hospital is actually managing two connected projects.


Project 1: The Permanent Cath Lab

This includes renovation, construction, equipment replacement, installation, testing, and the eventual return to clinical operations.


Project 2: The Temporary Cath Lab

This includes selecting a temporary solution, preparing the site, coordinating delivery, integrating hospital systems, preparing staff, and transitioning cases.

The projects overlap.


A simplified continuity sequence looks like:


Permanent lab operating

Modular cath lab prepared

Temporary lab ready for clinical use

Permanent lab taken offline

Renovation/construction proceeds

Procedures continue in modular lab

Permanent lab installation and readiness completed

Cases transition back

Temporary modular lab removed

Planning that overlap can reduce the risk of creating a gap between permanent-lab shutdown and temporary-lab readiness.

Why a Modular Cath Lab

Can Fit a Renovation Project

A modular cath lab is a fully equipped cardiac catheterization suite housed in a modular structure and delivered to the hospital site.


Atlas Medical's modular units are designed to provide a temporary environment that more closely resembles a permanent procedure room. Atlas states that its modular cath labs are at least 16 feet wide by 53 feet long, with large procedure-room footprints intended to give physicians and staff more working space.


For a renovation project, that can be particularly relevant when the temporary environment will be used for an extended period.


The decision should still be based on the individual hospital's requirements.



Hospitals should evaluate:

  • Expected renovation duration
  • Available site space
  • Patient access
  • Procedure mix
  • Equipment requirements
  • Staff workflow
  • Site preparation
  • IT connectivity
  • Regulatory requirements
  • Project budget


The objective isn't simply to find somewhere else to perform cases.


It's to create a workable temporary environment for the period between permanent-lab shutdown and reopening.

Map the Procedures That Cannot Stop

Before selecting equipment or planning the temporary site, define the clinical requirement.


Hospital leadership and cath lab teams should understand which procedures need to remain available during construction.


That discussion can influence the type of temporary lab required.


Atlas's modular cath lab fleet includes systems from Philips, Siemens, GE, and Canon, and its current modular offerings can include advanced packages such as Cone Beam CT depending on the configuration.


Rather than choosing temporary technology based only on availability, hospitals can compare the proposed configuration with:

  • Current clinical procedures
  • Physician requirements
  • Existing technology
  • Planned workflows
  • Anticipated case mix during construction

If the hospital's permanent lab uses a particular OEM platform, familiarity with the temporary system may also be relevant to the transition.

Protect the Workflow, Not Just the Procedure Room

A successful renovation-continuity strategy considers what happens before and after the patient enters the cath lab.



The modular unit needs to fit into the hospital's broader clinical operation.


Map the temporary patient journey:


Patient arrival

Preparation

Movement to temporary lab

Procedure

Recovery

Return or discharge


Then map the staff journey.


Where will nurses, technologists, physicians, supplies, and equipment move throughout the day?

Atlas states that its modular cath labs are designed for efficient patient flow and can integrate into existing hospital workflows.


Hospital teams should still test that workflow against their own site before construction begins.

A technically capable modular lab positioned in an operationally difficult location can create avoidable problems for months.

Make the Temporary Lab

Part of the Construction Schedule

The modular cath lab shouldn't appear on the project timeline as a single milestone labeled "delivery."


Several things need to happen before clinical operations can move into the temporary space.


The renovation schedule should account for activities such as:


Temporary solution selected

→ Site evaluated

→ Site preparation completed

→ Regulatory requirements addressed

→ Modular unit delivered

→ Utilities connected

→ IT/PACS integration completed

→ Equipment readiness verified

→ Applications training completed

→ Hospital-specific readiness completed

→ Temporary clinical operations begin

→ Permanent cath lab shuts down


This creates intentional overlap.

The hospital isn't waiting for the permanent lab to close before discovering whether the temporary environment is ready.

Site Planning Can Determine Whether the Strategy Works

Modular solutions provide more space, but that space also needs to exist somewhere on the hospital campus.


Atlas's modular cath labs are at least 16 feet wide by 53 feet long. The company's current site-preparation guidance also identifies space, power, and water as key requirements.


Facilities teams should evaluate the actual proposed configuration and determine whether the site can accommodate it.


The assessment may need to consider:

  • Modular footprint
  • Delivery route
  • Ground or pad requirements
  • Electrical infrastructure
  • Water requirements
  • Network access
  • Patient route
  • Staff route
  • Connection to existing hospital operations
  • Construction traffic
  • Emergency access


This planning should happen while renovation logistics are still being developed.


Construction staging and temporary clinical operations may otherwise compete for the same physical space.

Keep IT Out of the Last-Minute Category

The temporary lab still needs to operate inside the hospital's information environment.


Atlas states that its modular cath labs connect with existing PACS/EHR systems and that the company partners with hospital IT teams for integration.


For a renovation project, IT should therefore be part of the temporary-lab plan before deployment.


Relevant questions may include:

  • What network connectivity will be required?
  • How will imaging reach PACS?
  • What worklist/EHR connectivity is needed?
  • What hospital security requirements apply?
  • When can connectivity be tested?
  • Who owns each integration task?


The goal should be for the temporary environment to fit into the hospital's clinical information workflow before cases transition out of the permanent room.

Prepare the Clinical Team for the Temporary Environment

Even experienced cath lab teams need to become comfortable with a different room and potentially different imaging technology.


Atlas includes applications training with its modular cath lab rentals and states that its applications team consists of former cardiac cath or IR technologists with experience using the systems being rented.


Training should be coordinated with the transition schedule.


The hospital can consider:

  • Equipment familiarity
  • System controls
  • Clinical applications
  • Room layout
  • Staff positioning
  • Patient movement
  • Temporary workflows
  • Hospital-specific procedures


The objective isn't simply to show staff where controls are located.


It's to reduce friction when the clinical team moves from its permanent environment into the modular lab.

Plan for Construction Delays

Before They Happen

A renovation schedule is a forecast.


The temporary capacity plan should recognize that.


Construction, equipment installation, inspections, testing, or other dependencies can affect when the permanent cath lab is actually ready to reopen.


Hospitals should therefore understand what happens if the modular lab is needed longer than originally planned.


Before the rental begins, clarify:

  • Expected rental period
  • Extension options
  • Notice requirements
  • Potential scheduling constraints
  • How the transition date will be coordinated
  • What happens if the permanent project finishes early or late

The temporary plan should be flexible enough to support the real renovation—not just the original construction calendar.

Modular or Mobile During a Renovation?

A modular cath lab isn't automatically the right solution for every renovation.


Atlas provides both mobile cath lab rentals and modular solutions. Its mobile units are also designed to maintain procedural capacity during renovations and temporary expansion.


Hospitals should evaluate which configuration better fits their project.

Planning Question Why It Matters
How long will the renovation take? Temporary duration can influence the preferred solution.
How much working space does the team need? Modular units can provide a larger temporary environment.
What space is available on campus? Physical site constraints can affect configuration.
How will patients enter the temporary lab? Patient access affects day-to-day operations.
Which imaging system is required? Equipment availability and clinical requirements matter.
What infrastructure can the hospital provide? Site preparation needs differ by configuration and project.
What procedures need to continue? Clinical requirements should drive solution selection.

The decision should start with the hospital's renovation requirements rather than assuming one format is universally better.

Don't Forget the Second Transition

Hospitals often focus heavily on moving into the temporary lab.


Eventually, they also need to move out of it.


The return to the renovated cath lab deserves its own transition plan.


Before ending temporary operations, consider:

When the permanent lab will be clinically ready

Equipment testing and acceptance

Staff preparation for the new permanent system

IT readiness

Scheduling the final temporary cases

Transitioning supplies and workflows

Modular unit removal

Site restoration responsibilities


Avoid scheduling the modular lab's departure solely around the construction-completion date.

The permanent cath lab should be ready for the clinical transition according to the hospital's required processes.

Power Requirements Can Affect More Than Installation

Before finalizing the temporary strategy, hospital teams can evaluate whether the plan protects the major areas affected by renovation.

Continuity Area Question to Answer Before Construction
Procedural capacity Where will required cases be performed while the permanent lab is unavailable?
Technology Does the temporary system support the required clinical work?
Patient flow Can patients move safely and practically between hospital services and the temporary lab?
Staff workflow Can the cath team work efficiently in the temporary environment?
Facilities Is the site prepared for the modular unit and required utilities?
IT Can the temporary lab integrate with hospital systems?
Training Will staff be comfortable before the permanent lab closes?
Schedule Will the temporary lab be ready before construction affects clinical capacity?
Contingency What happens if the renovation takes longer than expected?
Return transition How will procedures move back into the permanent lab?

If one of these areas has no clear answer, the continuity plan may still have a gap.



Planning a Modular Cath Lab During Renovation With Atlas Medical

Atlas Medical's modular cath lab rentals are designed for hospitals that need to maintain cardiac and interventional capacity during renovations, upgrades, overflow, and other temporary requirements.


Atlas currently operates a nationwide fleet of more than 60 mobile and modular Cath and IR labs and offers systems from major imaging manufacturers.


For renovation projects, the most useful time to evaluate temporary capacity is before the permanent cath lab goes offline.


Hospitals can begin the conversation with information such as:

  • Planned renovation dates
  • Expected downtime
  • Procedure requirements
  • Current imaging platform
  • Preferred temporary technology
  • Proposed modular location
  • Known site limitations
  • Expected project duration


That gives the hospital and Atlas a stronger starting point for evaluating how temporary capacity can fit into the broader renovation plan.


For additional planning guidance, hospital teams can also explore the Atlas Medical Resources library, which includes information on mobile and modular imaging, temporary capacity, technology, and interventional projects.

Frequently Asked Questions

When should a hospital plan a modular cath lab for a renovation?

Temporary capacity planning should begin while the renovation schedule is being developed rather than waiting until the permanent cath lab is close to shutting down. This gives the project team time to evaluate the site, equipment, infrastructure, integration, regulatory requirements, training, and transition.

Can a modular cath lab remain on the hospital campus throughout a long renovation?

Rental duration depends on the individual project and agreement. Hospitals planning longer renovations should discuss the expected timeline and potential extension requirements with the provider before deployment.

Can the temporary modular lab connect to the hospital's existing systems?

Atlas states that its modular cath labs can connect to existing PACS/EHR environments and that its team works with hospital IT on integration. Project-specific requirements should be reviewed during planning.

Should the modular cath lab be ready before the permanent room closes?

Planning for the temporary environment to be ready before the permanent room becomes unavailable can help reduce the risk of a capacity gap. The exact transition schedule should account for the hospital's required setup, testing, training, and readiness processes.

What happens if the renovation takes longer than planned?

Hospitals should discuss rental flexibility and extension terms during procurement. Contingency planning is particularly important when temporary capacity depends on a construction schedule that may change.

How should hospitals choose between a mobile and modular cath lab during renovation?

Consider project duration, available space, clinical requirements, patient access, staff workflow, equipment requirements, infrastructure, and the desired temporary environment. Atlas offers both mobile and modular cath lab options, allowing hospitals to evaluate the configuration that better fits the individual project.

Mobile CT Scanner Price

Curious what you’ll pay for a mobile ct scanner truck or trailer? Pricing depends on several key factors:

 

  • Scanner Model & Slice Count: Cutting-edge, higher-slice scanners demand higher monthly fees.
  • Length of Rental: Longer commitments often reduce monthly costs.
  • Service & Maintenance Packages: Opting for a full-service plan can raise costs but remove the burden of repairs.
  • Geographic Location: Transport fees and regulatory requirements may bump up the final price.


Our typical Mobile CT rentals range from $20k to $40k per month.

Learn more about what goes into Mobile CT Rental Pricing HERE.

Turnkey Mobile CT Scanner

 

A “turnkey” mobile CT unit means all in one, no guesswork necessary. From power hookups and specialized staff training to compliance with local regulations, Atlas Medical delivers a seamless experience. Roll in, plug in, and start scanning—it’s that straightforward.

 

We offer Mobile CT rentals featuring all the major OEMs:
GE
Siemens Philips Canon


GE Healthcare logo with black stylized GE emblem and text on a white background
Siemens Healthineers logo in black with a dotted emblem on white background
PHILIPS logo in bold black uppercase letters on a white background
Black Canon logo text on a white background

Why Choose Atlas Medical

White check mark inside a black circle on a white background.

Extensive Inventory

Whether you’re after a 16-slice workhorse or a high-slice advanced system, we have the mobile ct scanner trailer or truck to match your needs. We offer mobile CT scanner from major OEMs such as GE, Siemens, Canon, and Philips.

White checkmark inside a black circle icon.

Flexible Agreements

From short-term mobile ct rental options to purchase and long-term leases, we tailor solutions that fit your budget and strategic goals.

White checkmark in a black circle icon

Dedicated Support

Our expert team isn’t just about dropping off a trailer. We handle setup, maintenance, and regulatory compliance so you can focus on patient care. To get started we can help you choose the best mobile CT scanner for YOU and guide you through site prep requirements.

White checkmark inside a black circle icon

Proven Reputation

Hundreds of clinics, hospitals, and imaging centers nationwide trust Atlas Medical to expand their diagnostic services. We'll even guide you through Mobile CT legal regulations and requirements.

Ready to elevate your imaging capabilities?

Let us help you bring advanced diagnostic services directly to your patients—without the cost and wait of permanent construction. When you need to rent, lease, or buy a mobile ct unit, trust Atlas Medical to deliver modern solutions for modern healthcare.


Close-up portrait of a man with short gray hair and a neutral expression against a blurred background

Sean Schneider

Mobile Project Manager · Atlas Medical


About the Author

Say hello to Sean Schneider - our Mobile Project Manager at Atlas Medical. Sean has worked in the medical imaging industry for over 20 years, including 10 years with Atlas Medical. 


Sean has a knack for making complicated projects simple to understand. Around here, Sean's the man who keeps things moving smoothly.


When Sean isn't helping launch our mobile imaging units at new sites he enjoys spending time with his family, golf, and hockey.

Request a Mobile Imaging Solution

Our Services Include:

Medical lab category buttons

By Jared Labtic September 9, 2026
Installing or gaining access to a cath lab imaging system is only part of getting the room ready for clinical use.  The people operating the technology also need to understand how that particular system fits into their daily workflow. A clinical team may already have years of cath lab experience and still need time to become comfortable with a different interface, room controls, imaging modes, table and C-arm movements, image review tools, and system-specific workflows. That is where cath lab applications training becomes valuable. Rather than teaching cath lab fundamentals, applications training focuses on helping experienced clinical teams understand and effectively use the imaging technology available to them. Hospitals that need project-based support can explore Atlas Medical's imaging applications training and temporary technologist staffing .
By Jared Labtic September 1, 2026
A mobile CT scanner may arrive on a trailer, but it still needs the electrical infrastructure required to operate advanced diagnostic imaging equipment. For hospital facilities and engineering teams, that makes power one of the first technical questions to resolve before delivery. Atlas Medical notes that a typical mobile CT unit requires 480V, 3-phase power . However, hospitals should not treat that figure as a universal specification for every trailer or scanner. The electrical requirements should always be confirmed for the specific mobile CT unit assigned to the project. Getting that information early gives facilities teams time to evaluate the site's existing electrical capacity, determine whether electrical work is necessary, coordinate responsibilities, and have the connection ready before the mobile unit arrives.
By Jared Labtic August 30, 2026
An experienced CT technologist already understands patient care, positioning, scan preparation, and the clinical demands of a busy imaging department. What changes when the scanner changes is the technology used to perform that work. A new interface, different protocol structure, unfamiliar reconstruction tools, or a change in manufacturer can create a learning curve even for an experienced team. CT applications training gives technologists hands-on, system-specific support so they can understand how the scanner fits into their department's clinical workflow. Hospitals may need this support when installing a scanner, replacing older equipment, changing OEM platforms, introducing advanced applications, opening a temporary imaging location, or onboarding additional staff. Atlas Medical provides imaging applications training and temporary technologist staffing for hospitals and imaging providers with project-based clinical support needs.
Mobile cath lab rental unit outside a hospital with healthcare professionals planning temporary cath
By Jared Labtic August 20, 2026
Planning a mobile cath lab rental? Learn the key stages hospitals should prepare for, from project assessment and site readiness to delivery and go-live.
June 15, 2026
Comparing Philips Allura vs Azurion? Learn about each systems's workflow,dose management, 3D guidance, and long-term value for modern interventional labs.
mobile cath lab
By Sharmaine Bonachita May 28, 2026
Learn what is a mobile cath lab, when hospitals use one, and how it helps maintain cardiac care during renovations, replacements, or downtime.