What to Include in a Mobile Cath Lab RFP

A hospital preparing to rent a mobile cath lab needs more than a price and an available trailer.



The hospital needs to know whether the temporary lab can support its procedures, fit the site, integrate with existing systems, arrive on schedule, support staff workflow, and remain available for the full project period.


A well-written mobile cath lab RFP helps procurement teams compare vendors against the same requirements instead of evaluating proposals that describe completely different solutions.


The RFP should therefore be developed with input from more than procurement alone.


Cath lab leadership, facilities, IT, clinical engineering, project management, infection prevention, finance, and other appropriate hospital stakeholders may all have requirements that affect the temporary lab.


Hospitals still defining the type of temporary solution they need can review Atlas Medical's mobile cath lab rental solutions before developing the RFP.

Start the RFP With the Hospital's Project, Not the Equipment

An RFP can become overly focused on equipment specifications before vendors understand why the hospital needs temporary capacity.



Begin by describing the project.


Provide enough information for a prospective vendor to understand:

  • Why the permanent cath lab will be unavailable
  • Expected shutdown date
  • Required temporary go-live date
  • Anticipated rental duration
  • Renovation or replacement schedule
  • Expected procedure volume
  • Proposed location for the temporary lab
  • Known site limitations
  • Expected project milestones
  • Possibility of schedule extensions


This context matters because a mobile cath lab rental is part of a larger hospital project.


For renovation and replacement projects, the temporary and permanent timelines should be coordinated rather than managed independently.


Atlas Medical's existing Mobile Cath Lab Rental Timeline provides a useful overview of the stages hospitals may need to coordinate from initial planning through clinical go-live.

1. Define the Clinical Requirements


Before specifying a particular system, define what the temporary lab actually needs to support.


The RFP can ask vendors to confirm whether the proposed configuration is appropriate for the hospital's intended clinical use.


Information may include:

  • Types of procedures expected
  • Estimated case volume
  • Physician requirements
  • Existing cath lab platform
  • Preferred imaging manufacturer
  • Required clinical applications
  • Supporting equipment requirements
  • Patient types expected
  • Expected hours of operation


This information helps prevent a common procurement problem:


Comparing units based on availability and price without first confirming that they fit the hospital's clinical workflow.

Atlas Medical's Temporary Cath Lab Options resource provides additional context on temporary configurations and the equipment hospitals may consider when planning procedural continuity.


2. Specify the Imaging System


"Mobile cath lab" is not a complete equipment specification.


The RFP should clearly state the hospital's requirements or ask vendors to provide detailed information about the proposed imaging system.


Request information such as:

  • Manufacturer
  • System model
  • Software version
  • Detector configuration
  • Installed clinical packages
  • Available imaging applications
  • System age or installation information when relevant
  • Configuration of the proposed temporary lab


If the hospital prefers a specific OEM, state that preference.


Atlas Medical's current mobile cath lab fleet includes imaging systems from major manufacturers such as Philips, Siemens, Canon, and GE.


The hospital may also want to explain what equipment its staff currently uses.


If the permanent department operates on Philips equipment, for example, maintaining a similar platform temporarily may reduce the amount of change the clinical team experiences during the transition.


3. Ask Vendors to Describe the Complete Temporary Lab


The imaging system is only one component of the solution.


Procurement should understand exactly what is included in the proposed mobile environment.


Ask the vendor to describe:

  • Procedure room
  • Imaging system
  • Patient table
  • Displays and monitors
  • Control area
  • Patient entry
  • Staff entry
  • Scrub facilities when applicable
  • HVAC
  • Storage
  • Patient lift or accessibility equipment when applicable
  • Included supporting equipment
  • Optional equipment


If the vendor offers multiple configurations, require each option to be clearly identified.


That makes it easier to determine whether two proposals are actually comparable.


4. Include Unit Dimensions and Site Requirements


A mobile cath lab may meet the hospital's clinical requirements and still be unusable if the site cannot accommodate it.

The RFP should request the physical specifications of the proposed unit.


Ask for:

  • Overall length
  • Width
  • Height
  • Expanded dimensions when applicable
  • Weight
  • Required parking or pad area
  • Leveling requirements
  • Delivery clearances
  • Turning requirements
  • Patient-entry configuration
  • Staff-entry configuration
  • Required distance from the hospital
  • Access requirements for delivery and removal


The vendor should also identify the infrastructure the hospital is expected to provide.


For example, Atlas Medical's Philips Azurion site preparation checklist covers considerations involving footprint, delivery access, electrical service, networking, utilities, and other site-specific requirements.


Actual requirements vary by unit and project, so the RFP should require specifications for the exact unit being proposed rather than assuming one checklist applies to every mobile cath lab.


5. Define Electrical and Utility Responsibilities


Temporary imaging equipment requires appropriate infrastructure.


The RFP should clearly separate what the hospital provides from what the vendor provides.


Ask the vendor to specify:

  • Required voltage
  • Phase
  • Amperage
  • Connection type
  • Cable requirements
  • Maximum cable distance
  • Generator considerations
  • Water requirements
  • Drain requirements
  • HVAC requirements
  • Medical gas requirements, if applicable
  • Other required utilities


Avoid writing only:


"Hospital will provide power."


Instead, require the vendor to state exactly what electrical infrastructure the proposed unit requires.


Facilities and electrical teams can then evaluate the requirement before the contract is awarded.


6. Require a Site-Planning Process


A strong RFP should ask more than whether the unit will "fit."


Ask vendors to explain their site-planning process.


Questions may include:

  • Is a remote site review available?
  • Is an on-site survey available?
  • Who reviews the proposed location?
  • Are site drawings provided?
  • Who confirms delivery access?
  • Who confirms final placement?
  • What documentation must the hospital submit?
  • How are site deficiencies communicated?
  • When must site readiness be completed?


This can be particularly important when the temporary lab needs to arrive before a permanent cath lab is shut down.

Site problems discovered late in the project can affect deployment.


7. Include Patient and Staff Workflow Requirements


A technically suitable parking location is not necessarily an operationally suitable location.


The RFP should explain how the hospital expects patients and staff to use the temporary lab.


Consider:

  • Patient route from the hospital
  • Stretcher access
  • Wheelchair access
  • Staff access
  • Supply movement
  • Patient preparation
  • Recovery location
  • Emergency response
  • Weather exposure
  • Communication with hospital departments
  • Connection between the temporary and permanent facility


Ask vendors to describe how their proposed unit supports these requirements.


The temporary lab may be used for months, so day-to-day workflow deserves consideration during procurement rather than after delivery.


8. Define IT, PACS, EHR, and Network Requirements


IT should be included in the RFP process early.


Atlas Medical states that its mobile cath labs can connect with existing PACS/EHR environments.


The hospital should still document its own technical requirements and ask the vendor to identify what is necessary for the proposed system.


The RFP may request information about:

  • Network connections
  • PACS connectivity
  • DICOM workflow
  • Worklist requirements
  • EHR connectivity when applicable
  • Network drops
  • Remote support connectivity
  • Cybersecurity requirements
  • Vendor access
  • Testing responsibilities
  • Go-live support


The RFP should also identify who is responsible for each part of the integration.


Vendor responsibility + hospital IT responsibility + testing responsibility


should be clear before deployment.


9. Ask What Applications Training Is Included


Experienced cath lab technologists may still need training when moving onto a different imaging system or temporary environment.


The RFP should ask:

  • Is applications training included?
  • How many training days are included?
  • Is training performed on-site?
  • What OEM/system experience does the specialist have?
  • How many staff members can participate?
  • Can multiple shifts be supported?
  • Is training available before go-live?
  • Is go-live support available?
  • Is additional training available if needed?
  • What is the cost of additional training?


Hospitals requiring additional system-specific support can also review Atlas Medical's Imaging Applications Training & Technologist Staffing.


Applications support and clinical staffing should be treated as separate requirements if the hospital needs both.


10. Define Service and Maintenance Expectations


The hospital should understand what happens if the temporary imaging system has a technical problem during the rental.


Ask vendors to explain:

  • Service coverage
  • Support hours
  • Technical support process
  • Response expectations
  • Preventive maintenance responsibilities
  • Parts support
  • Remote service capabilities
  • On-site service availability
  • Escalation process
  • After-hours procedures
  • Responsibility for equipment downtime


Avoid relying only on general statements such as:


"Full service included."


Ask the vendor to define what that means.


11. Request Documentation Before Award


Procurement, clinical engineering, facilities, risk management, and other hospital teams may require documentation before approving a vendor.


Rather than requesting these documents one at a time later, identify them in the RFP.


Depending on hospital requirements, requested documentation might include:

  • Equipment specifications
  • Unit drawings
  • Utility requirements
  • Service documentation
  • Insurance documentation
  • Vendor credentials
  • Equipment records
  • Preventive maintenance information
  • Training documentation
  • Site-preparation documentation
  • Other hospital-required vendor information


The exact list should come from the hospital's own policies and procurement requirements.


12. Make the Project Schedule Part of the Vendor Response


Do not ask only:


"Can you deliver by this date?"


Ask the vendor to provide a proposed project schedule.


The response might identify milestones such as:

Award

→ Site review

→ Final equipment confirmation

→ Site preparation

→ IT coordination

→ Delivery

→ Installation/setup

→ Testing

→ Applications training

→ Hospital readiness activities

→ Clinical go-live


This makes it easier to compare how each vendor plans to move from contract award to operational readiness.


Hospitals can use the Mobile Cath Lab Rental Timeline: What Hospitals Should Plan For as a supporting planning resource when developing these milestones.


13. Address Rental Duration and Extension Terms


Hospital construction schedules can change.


The permanent cath lab may not reopen exactly when originally planned.


The RFP should therefore ask vendors to define:

  • Minimum rental term
  • Initial rental period
  • Monthly extension options
  • Extension notice requirements
  • Availability beyond the original term
  • Early termination terms
  • Mobilization charges
  • Demobilization charges
  • Other schedule-related costs


This information can be just as important as the initial monthly rental rate.


A low monthly price may become less attractive if the project requires an extension and the commercial terms change substantially.


14. Make Pricing Comparable


One of the most important functions of an RFP is making proposals easier to compare.


Ask vendors to separate major cost components rather than providing only one total.


A pricing response might include:

Cost Category Vendor Response
Monthly rental $
Mobilization/delivery $
Installation/setup $
Demobilization/removal $
Applications training Included / $
Service & maintenance Included / $
Additional training days $
Rental extension $
Site survey Included / $
Optional equipment $
Other project fees $

The hospital can customize this structure based on its procurement policies.



The important point is consistency.


If every vendor responds to the same pricing categories, procurement has a much clearer basis for comparison.

15. Ask Vendors to State Hospital Responsibilities



A strong proposal should explain what the vendor does not provide as clearly as what it does.


Ask each vendor to list the hospital's responsibilities.


These may involve:

  • Site preparation
  • Electrical work
  • Network installation
  • Water/drain connections
  • Permits
  • Inspections
  • Accessibility requirements
  • Patient pathways
  • Hospital credentialing
  • IT configuration
  • Clinical policies
  • Staffing
  • Security
  • Other project-specific requirements


This reduces the chance of discovering an unassigned responsibility after the contract has already been signed.

16. Include a Responsibility Matrix

For complex projects, consider requiring vendors to complete a responsibility matrix.

Project Item Hospital Vendor Shared / Notes
Site selection
Site review
Electrical infrastructure
Unit specifications
Network connection Coordinate with vendor
Equipment delivery
Applications training Define scope
Hospital credentialing
Equipment service Define coverage
Clinical staffing Unless separately contracted
Unit removal

The final matrix should reflect the actual agreement.



Its value is simple:


Everyone can see who owns each task.

17. Define How Proposals Will Be Evaluated

Hospitals do not have to select the lowest-priced proposal.


The RFP can explain the evaluation criteria in advance.



For example:

Evaluation Area What the Hospital May Compare
Clinical fit Ability to support required procedures
Technology OEM, model, software and applications
Availability Ability to meet required dates
Site compatibility Fit with proposed location and infrastructure
Workflow Patient and staff usability
IT Integration requirements and support
Training Applications support
Service Maintenance and technical support
Project management Deployment and communication process
Commercial terms Rental, delivery, extensions and other costs

Hospitals can assign their own weighting based on project priorities.



For one hospital, OEM familiarity may be critical.


For another, deployment timing may be the deciding factor.


The RFP should make those priorities visible.

18. Don't Evaluate Price Until You Know the Proposals Are Comparable


Consider two hypothetical proposals.


Vendor A proposes a lower monthly rental but excludes applications training, certain service support, and some transportation costs.


Vendor B has a higher monthly rental but includes those items.


Looking only at the monthly rate would not provide a fair comparison.


Procurement should first ask:

Are these vendors proposing equivalent solutions?


Then compare total project costs and commercial terms.


This is why detailed scope requirements are important.

A Practical Mobile Cath Lab RFP Checklist


Before issuing the RFP, confirm that it addresses:


Project

  • Project purpose
  • Required go-live date
  • Expected rental duration
  • Permanent project schedule
  • Extension possibility


Clinical

  • Procedures
  • Expected volume
  • Physician requirements
  • Preferred technology
  • Clinical applications


Equipment

  • OEM
  • Model
  • Software
  • Detector/configuration
  • Supporting equipment
  • Unit layout


Site

  • Dimensions
  • Footprint
  • Delivery access
  • Electrical requirements
  • Utilities
  • Patient access
  • Staff access


Technology

  • PACS
  • DICOM
  • Worklist
  • EHR
  • Network
  • Cybersecurity
  • Testing


Support

  • Applications training
  • Service
  • Maintenance
  • Technical support
  • Project management


Commercial

  • Monthly rental
  • Delivery
  • Setup
  • Removal
  • Extensions
  • Training costs
  • Optional equipment
  • Other fees


Responsibilities

  • Hospital responsibilities
  • Vendor responsibilities
  • Shared responsibilities
  • Required documentation
  • Project milestones


If an important requirement cannot be placed into one of these categories, add it separately rather than leaving it for post-award discussion.


Questions Procurement Teams Can Ask Mobile Cath Lab Vendors


Before finalizing a vendor, consider asking:

  1. What exact mobile cath lab configuration are you proposing?
  2. What OEM, model, and software will be provided?
  3. Is that exact unit available for our required dates?
  4. What clinical applications are included?
  5. What does our hospital need to prepare before delivery?
  6. What are the exact electrical and utility requirements?
  7. How will the unit connect with our PACS/EHR environment?
  8. What applications training is included?
  9. What service and maintenance support is included?
  10. Who manages delivery and installation?
  11. What happens if our permanent project is delayed?
  12. What are the extension terms?
  13. What costs are not included in the quoted monthly rate?
  14. What documentation will you provide?
  15. Who will manage the project from award through removal?


The answers can reveal important differences between proposals that may not be visible from price alone.


Mobile Cath Lab RFP vs. Vendor Quote


An RFP and a vendor quote serve different purposes.


A mobile cath lab RFP defines what the hospital needs and how vendors should respond.


A vendor proposal or quote explains how that vendor intends to meet those requirements and at what cost.


The stronger the RFP, the easier it becomes to evaluate whether the proposal actually meets the hospital's needs.


That is particularly important for temporary cath lab projects because the hospital is not simply renting imaging equipment.


It is coordinating a temporary clinical environment that may need to operate throughout a renovation, replacement, or expansion project.


Planning a Mobile Cath Lab Project With Atlas Medical


Atlas Medical provides mobile cath lab rentals for hospitals that need temporary cardiac and interventional capacity during renovations, equipment upgrades, overflow, and other temporary requirements.


Atlas's current mobile cath lab offering includes systems from major imaging manufacturers, PACS/EHR connectivity, applications training, and support for temporary hospital operations.


Hospitals still deciding which temporary configuration is appropriate can review Temporary Cath Lab Options.


If a larger temporary environment is required, hospitals can also compare modular cath lab solutions.


For hospitals already building a project schedule, the Mobile Cath Lab Rental Timeline provides additional guidance on site readiness, delivery, IT coordination, training, and go-live planning.


These resources can help procurement teams develop a more complete scope before requesting proposals.

Frequently Asked Questions

What should be included in a mobile cath lab RFP?

A mobile cath lab RFP should define the project schedule, clinical requirements, imaging technology, unit configuration, site and utility requirements, IT connectivity, applications training, service expectations, rental duration, pricing format, documentation requirements, and hospital/vendor responsibilities.

Who should help develop a mobile cath lab RFP?

Procurement may lead the RFP process, but requirements may need input from cath lab leadership, physicians, facilities, IT, clinical engineering, project management, finance, infection prevention, and other appropriate hospital stakeholders.

Should an RFP specify the cath lab manufacturer?

If OEM familiarity or a particular clinical platform is important to the hospital, that requirement or preference should be stated. Vendors should then identify the exact manufacturer, model, software, and relevant applications included in their proposal.

Should site requirements be included before selecting a vendor?

The hospital should provide known site information and require vendors to state the requirements for their proposed unit. Because specifications can vary between units, final site requirements should be verified for the actual equipment proposed.

Should applications training be included in the RFP?

Yes, when training is important to the project. Define whether applications training is required and ask vendors to specify what is included, the number of days, specialist experience, scheduling, additional training costs, and availability around go-live.

How should hospitals compare mobile cath lab pricing?

Compare the full project scope rather than monthly rent alone. Delivery, setup, removal, applications training, service, optional equipment, extensions, and other project costs may affect the total commercial comparison.

What if the hospital's renovation takes longer than expected?

The RFP should request extension terms, notice requirements, additional monthly costs, and information about continued unit availability. This helps procurement understand the commercial impact of a permanent-project delay before signing the agreement.

Should hospitals request a site survey before deployment?

Site review is an important part of mobile cath lab planning. Hospitals should ask prospective vendors to explain their site-review process, required information, responsibilities, and when final site approval occurs.

Mobile CT Scanner Price

Curious what you’ll pay for a mobile ct scanner truck or trailer? Pricing depends on several key factors:

 

  • Scanner Model & Slice Count: Cutting-edge, higher-slice scanners demand higher monthly fees.
  • Length of Rental: Longer commitments often reduce monthly costs.
  • Service & Maintenance Packages: Opting for a full-service plan can raise costs but remove the burden of repairs.
  • Geographic Location: Transport fees and regulatory requirements may bump up the final price.


Our typical Mobile CT rentals range from $20k to $40k per month.

Learn more about what goes into Mobile CT Rental Pricing HERE.

Turnkey Mobile CT Scanner

 

A “turnkey” mobile CT unit means all in one, no guesswork necessary. From power hookups and specialized staff training to compliance with local regulations, Atlas Medical delivers a seamless experience. Roll in, plug in, and start scanning—it’s that straightforward.

 

We offer Mobile CT rentals featuring all the major OEMs:
GE
Siemens Philips Canon


GE Healthcare logo with black stylized GE emblem and text on a white background
Siemens Healthineers logo in black with a dotted emblem on white background
PHILIPS logo in bold black uppercase letters on a white background
Black Canon logo text on a white background

Why Choose Atlas Medical

White check mark inside a black circle on a white background.

Extensive Inventory

Whether you’re after a 16-slice workhorse or a high-slice advanced system, we have the mobile ct scanner trailer or truck to match your needs. We offer mobile CT scanner from major OEMs such as GE, Siemens, Canon, and Philips.

White checkmark inside a black circle icon.

Flexible Agreements

From short-term mobile ct rental options to purchase and long-term leases, we tailor solutions that fit your budget and strategic goals.

White checkmark in a black circle icon

Dedicated Support

Our expert team isn’t just about dropping off a trailer. We handle setup, maintenance, and regulatory compliance so you can focus on patient care. To get started we can help you choose the best mobile CT scanner for YOU and guide you through site prep requirements.

White checkmark inside a black circle icon

Proven Reputation

Hundreds of clinics, hospitals, and imaging centers nationwide trust Atlas Medical to expand their diagnostic services. We'll even guide you through Mobile CT legal regulations and requirements.

Ready to elevate your imaging capabilities?

Let us help you bring advanced diagnostic services directly to your patients—without the cost and wait of permanent construction. When you need to rent, lease, or buy a mobile ct unit, trust Atlas Medical to deliver modern solutions for modern healthcare.


Close-up portrait of a man with short gray hair and a neutral expression against a blurred background

Sean Schneider

Mobile Project Manager · Atlas Medical


About the Author

Say hello to Sean Schneider - our Mobile Project Manager at Atlas Medical. Sean has worked in the medical imaging industry for over 20 years, including 10 years with Atlas Medical. 


Sean has a knack for making complicated projects simple to understand. Around here, Sean's the man who keeps things moving smoothly.


When Sean isn't helping launch our mobile imaging units at new sites he enjoys spending time with his family, golf, and hockey.

Request a Mobile Imaging Solution

Our Services Include:

Medical lab category buttons

Mobile CT scanner installation at a hospital showing delivery, utility setup, and preparation for cl
By Jared Labtic September 13, 2026
By the time a mobile CT scanner arrives at a hospital, much of the planning should already be complete. The site has been selected. Facilities has reviewed the proposed location. Power and connectivity requirements have been discussed. The hospital knows when temporary CT capacity needs to become available. But delivery is not the same as go-live. A mobile CT scanner installation still involves positioning the unit, connecting infrastructure, integrating the scanner with hospital systems, verifying equipment readiness, preparing technologists, and completing the hospital's own pre-clinical requirements. Understanding that sequence helps project teams avoid treating the arrival date as the same thing as the clinical start date. Hospitals evaluating temporary CT capacity can review Atlas Medical's mobile CT scanner solutions before building their deployment schedule. Atlas currently offers mobile CT systems from major OEMs and includes applications training and integration support as part of its turnkey approach.
By Jared Labtic September 9, 2026
Installing or gaining access to a cath lab imaging system is only part of getting the room ready for clinical use.  The people operating the technology also need to understand how that particular system fits into their daily workflow. A clinical team may already have years of cath lab experience and still need time to become comfortable with a different interface, room controls, imaging modes, table and C-arm movements, image review tools, and system-specific workflows. That is where cath lab applications training becomes valuable. Rather than teaching cath lab fundamentals, applications training focuses on helping experienced clinical teams understand and effectively use the imaging technology available to them. Hospitals that need project-based support can explore Atlas Medical's imaging applications training and temporary technologist staffing .
By Jared Labtic September 8, 2026
A cath lab renovation creates an unusual planning challenge for hospitals: the project is designed to improve cardiac services, but completing it may temporarily take critical procedural space out of operation. The construction schedule is only part of the problem.  Hospital leaders also have to decide what happens to procedures, physicians, staff, patients, and workflows while the permanent lab is unavailable. A modular cath lab for hospital renovation can provide temporary procedural capacity on-site while work progresses inside the permanent facility. Atlas Medical specifically positions its modular cath lab rentals for renovations, temporary capacity, and projects where hospitals need to keep cases running. The key is to treat the modular lab as part of the renovation strategy—not as equipment that gets added after the construction plan is already finished.
By Jared Labtic September 1, 2026
A mobile CT scanner may arrive on a trailer, but it still needs the electrical infrastructure required to operate advanced diagnostic imaging equipment. For hospital facilities and engineering teams, that makes power one of the first technical questions to resolve before delivery. Atlas Medical notes that a typical mobile CT unit requires 480V, 3-phase power . However, hospitals should not treat that figure as a universal specification for every trailer or scanner. The electrical requirements should always be confirmed for the specific mobile CT unit assigned to the project. Getting that information early gives facilities teams time to evaluate the site's existing electrical capacity, determine whether electrical work is necessary, coordinate responsibilities, and have the connection ready before the mobile unit arrives.
By Jared Labtic August 30, 2026
An experienced CT technologist already understands patient care, positioning, scan preparation, and the clinical demands of a busy imaging department. What changes when the scanner changes is the technology used to perform that work. A new interface, different protocol structure, unfamiliar reconstruction tools, or a change in manufacturer can create a learning curve even for an experienced team. CT applications training gives technologists hands-on, system-specific support so they can understand how the scanner fits into their department's clinical workflow. Hospitals may need this support when installing a scanner, replacing older equipment, changing OEM platforms, introducing advanced applications, opening a temporary imaging location, or onboarding additional staff. Atlas Medical provides imaging applications training and temporary technologist staffing for hospitals and imaging providers with project-based clinical support needs.
Mobile cath lab rental unit outside a hospital with healthcare professionals planning temporary cath
By Jared Labtic August 20, 2026
Planning a mobile cath lab rental? Learn the key stages hospitals should prepare for, from project assessment and site readiness to delivery and go-live.